After several exchanges of e-mails with my CSO and after discussing the issue with the Site Supervisor, the vanity basins has finally been installed. The issue was escalated to the Construction Manager and they managed to get stocks from a different supplier with ours getting high priority. Props and kudos to Simonds for a job well done and for making this happen in a short span of time.

Also noticed that the splashback and door knobs has also been installed. Will post photos as they become available.

There are still a few outstanding issues remaining and we're hoping that this gets finished soon. We're almost a week delayed now from the Practical Completion Inspection (PCI) originally scheduled on 03 April.

Oustanding work to be done:

1. Unbricked portion on the kitchen/lounge alfresco area.

2. Sound System Installation

3. Plumbing fit off - showerheads, mixers and taps, toilet bowls.

4. Touch up painting - I guess this will be done once internal work is finished

5. Concrete pavement to porch and driveway - this will be done before final handover as they don't want contractors to be driving into it.

6. Final House clean and site clean

7. Removal of temporary fence and lavatory

My personal estimate is that this can be done in less than a week but knowing how builders operate this might not be the case.

Can't wait for handover.