view from west showing our two neighbours, with us in between
cabinet and room doors have been painted
cabinet and room doors have been painted
view from glass window in theatre, kitchen can be seen
another view from rear of garage
door going to lounge room
area infront and rear of garage cleared of rubbish
front of site cleared of rubbish
21 February 2009
The fixing stage is finished and we're now in the final stage. We weren't able to go inside the house as all the point of entries have been locked. I plan to go there during weekdays so that workers will be there. Peeking though the windows, I can see that all skirting and architraves are in place and that painting works might be starting soon. Some of the photos taken were from outside the window so some reflection can be seen.
At this point, we have received the invoice of Stage 4/85% completion.
Looking at the builder's website, the following is what's included in the final stage.
Tiling in bathroom, ensuite, shower and laundry areas.
Timber Flooring installation
Cleaning of bricks with acid wash
Installation of downpipes to stormwater drain
Painting
Shower Screens
Caesarstone benchtops
Mirrors
Door Knobs
Robe doors
Robe Shelving
Plumbing fit off to connect all taps, toilet, sinks, etc.
Electrical fit off - power points, light points
Garage door installation
Flyscreen
Paving
Ducted Heating installation
Ducted Vacuum installation
Ceiling insulation
Sound System, TV and telephone points
House Clean
Final Site Clean
Removal of Hire Items
Quality Assurance Assessment